cpp-xer-parser

license: MIT python: 3.10+ status: stable

A standalone parser and generator for Primavera P6 XER files. Pure Python 3.10+, MIT-licensed, no third-party runtime dependencies.

Maintained by Critical Path Partners — a forensic-scheduling consultancy.

Companion to cpp-cpm-engine.


Scope: what this is, and what it is not

What this is. A complete XER reader and writer. It parses every table in an export into structured Python data, builds the cross-reference maps (WBS, resources, logic, activity codes, user-defined fields), decodes calendars, and writes XER files back out in P6 24.12 table order. Every function in the feature table below is implemented in this repository. None of them is a shim that calls out to something private. Vendor it, fork it, or import it.

What this is not. It is not the whole toolchain Critical Path Partners runs. CPP's forensic deliverables are produced with additional validation that is kept private and is not part of this package. Named in capability terms, this package does not include:

  • A date-field validation gate. Date fields are parsed as they appear. There is no pass that flags unparseable or implausible date values before downstream math consumes them.
  • A calendar-decode warning channel. parse_calendar_data decodes the standard P6 encoding and then falls through two legacy patterns. When all of them fail it returns an empty work week rather than raising or warning, and a corrupt calendar record is not reported to the caller. Code that needs that signal has to inspect the returned structure itself.
  • Working-day arithmetic beyond get_work_days_between and duration_hours_to_days. The additional working-day delta helper in CPP's internal parser is not included here.

None of that makes this parser wrong. It makes it smaller. If you are comparing output from this package against a report CPP produced, the difference in validation surface is the thing to ask about, and the answer is in this section rather than in a footnote.


Why this parser

The XER format is fragile. Field counts shift between P6 versions. Calendar data ships inside a nested-paren mini-language. BOMs come and go without warning. Real-world exports from large programs use formats that simple split-on-tab parsers silently mangle.

It comes out of forensic schedule analysis, where a silently mangled field becomes a wrong number in a report that someone has to defend. The design goals follow from that: fields round-trip through parse and generate, the calendar encodings real exports actually use are decoded rather than guessed at, and generated files carry the field counts P6 expects on import. tests/ is what backs those goals. Read it before relying on them.


Install

git clone https://github.com/danafitkowski/cpp-xer-parser
cd cpp-xer-parser
# No external dependencies. Just put scripts/ on your sys.path.

The parser is pure Python 3.10+ with no third-party runtime dependencies.


Quick start

import sys
sys.path.insert(0, 'scripts')

from xer_parser import parse_xer, print_summary, get_table, build_wbs_map

# Parse
data = parse_xer('path/to/your.xer')

# Print a one-shot summary
print_summary(data)

# Drill into tables
tasks = get_table(data, 'TASK')
print(f'{len(tasks)} activities')

# Cross-reference maps
wbs = build_wbs_map(data)
for t in tasks[:3]:
    print(t['task_code'], '→', wbs[t['wbs_id']]['_full_path'])

What it does

Feature Function
Parse XER to structured dict parse_xer(path)
Generate XER from dict generate_xer(data, path, p6_version='24.12', currency='CAD', ...)
Table accessor get_table(data, 'TASK')
Calendar map (with holidays) get_calendar_map(data)
WBS hierarchy with full paths build_wbs_map(data)
Resource assignments per task build_resource_map(data)
Predecessor / successor maps build_predecessor_map(data)
Activity code map build_activity_code_map(data)
User-defined field map build_udf_map(data)
Work-day count between two dates get_work_days_between(start, end, calendar)
Duration hours-to-days conversion duration_hours_to_days(hours, calendar)
Structural validation report validate_schedule(data, profile='commercial')
Schedule structure score aace_31r_compliance(data, profile='commercial')
Schedule integrity manifest † generate_xer_manifest(data, xer_path=None, **manifest_kwargs)
Schema drift between two XERs schema_diff(data_a, data_b)
Half-step XER generator (SmartPM-equivalent) compute_half_step_xer(base_path, updated_path, output_path)

validate_schedule and aace_31r_compliance run from a plain clone: they use the bundled scripts/validation.py and scripts/config_profiles.py. generate_xer_manifest also needs CPP's internal audit-trail module, which is not bundled here. Without it the call raises RuntimeError rather than returning a manifest with missing provenance. Everything else in the table needs nothing but the standard library.


Half-step XER (vendor-equivalent: SmartPM/Plannex)

The most analytically interesting feature in the repo. The compute_half_step_xer function implements the bifurcation procedure of AACE 29R-03 §2.3.D.2 ("Bifurcation: Creating a Progress-Only Half-Step Update" — the RP itself names the procedure "half-stepping or two-stepping"), which is how MIP 3.4 (Observational / Dynamic / Contemporaneous Split) splits each update. Vendor half-step tools (SmartPM, Plannex) are equivalents of this procedure. It takes a period-start schedule plus the next period's update, and produces a schedule that has only the progress fields copied from the updated schedule onto the base structure.

The forensic value: anything that moves in the half-step moved because work didn't happen as planned. Anything that moves between the half-step and the full update moved because the contractor revised logic or scope.

from xer_parser import compute_half_step_xer

result = compute_half_step_xer(
    base_xer_path='period_start.xer',
    updated_xer_path='period_end.xer',
    output_xer_path='half_step.xer',
)

print(f"Matched: {result['matched_count']}")
print(f"Progressed: {result['progressed_count']}")
print(f"Activities added in updated (NOT copied): {result['unmatched_in_updated']}")
print(f"Activities removed in updated (preserved in output): {result['unmatched_in_base']}")

unmatched_in_updated is forensically significant: these are activities the contractor added between period boundaries, and they belong to the logic-revision layer, not the progress layer.


XER generation rules (P6 24.12)

The generator emits P6-importable XER files following these rules:

  1. Table order: CURRTYPE, FINTMPL, OBS, PROJECT, CALENDAR, SCHEDOPTIONS, PROJWBS, TASK, TASKPRED, then remaining tables. See the TABLE_ORDER constant.

  2. ERMHDR line: ERMHDR\t24.12\t<export_date>\tProject Management\tCAD (or supplied currency).

  3. Field counts: every %R row must have exactly the same number of fields as the %F definition that precedes it. The generator enforces this.

  4. Known field counts for P6 24.12:

    • PROJECT: 72 fields
    • SCHEDOPTIONS: 26 fields
    • PROJWBS: 27 fields
    • TASK: 62 fields (includes crt_path_num)
    • TASKPRED: 12 fields (includes comments, aref, arls)

    Open question, disclosed rather than resolved. The parser's own version-aware validation constant (TABLE_FIELD_COUNTS_BY_VERSION) holds one fewer for every table in that list: PROJECT 71, SCHEDOPTIONS 25, PROJWBS 26, TASK 61, TASKPRED 11. A file matching the numbers above therefore draws an XER-FIELD-COUNT warning from validate_schedule. The code carries a standing TODO(schema-truth) saying the same thing. Both sets have plausible lineage, neither has been re-checked against a fresh P6 24.12 export, and guessing would silently change validation behaviour for every consumer, so both are left as they stand and the conflict is stated here instead. If a field count matters to your work, verify it against your own export.

  5. Encoding: ASCII with CRLF line endings by default. Pass encoding='cp1252' for strict legacy P6 compatibility with non-ASCII text.

  6. Calendar data: when generating from scratch, copy the clndr_data field verbatim from a working reference XER. Re-encoding is brittle.

See references/table-reference.md for the table reference: 40 XER tables, 27 of them with a field-by-field list, and 13 less common ones (documents, roles, shifts, resource codes, risk) described at table level rather than field level.


Running the tests

python tests/test_xer_parser.py               # core parser + generator smoke test
python tests/test_half_step.py                # half-step generator (SmartPM-equivalent)
python tests/test_bundled_validation_runs.py  # bundled validation stubs bind on a plain clone

Or with pytest:

pip install pytest
pytest tests/

pytest tests/ runs 22 tests across 4 files and they all pass. CI runs the same suite on Linux, macOS and Windows against Python 3.10, 3.11 and 3.12.

All tests build their XER fixtures synthetically in memory; no real client XER files ship with the repo.


Relationship to CPP's internal toolchain

Critical Path Partners keeps a larger internal parser that this package was cut from. What is published here is the parsing and generation core. What is not published is the extra validation surface listed under Scope: the date-field gate, the calendar-decode warning channel, and the additional working-day arithmetic. Reports CPP issues are produced with the internal toolchain, not with this package on its own.

Two consequences worth being explicit about:

  1. Nothing here is a stub. The functions in the feature table are the working implementations, and the test suite exercises them. This is a smaller parser, not a demonstration copy.
  2. If you are auditing a CPP deliverable, this repository shows you the parsing and generation logic behind it, and the Scope section tells you what else ran that you cannot see here. Ask about the difference rather than inferring it.

scripts/validation.py and scripts/config_profiles.py are minimal standalone subsets of the same-named modules in the larger internal suite: enough for validate_schedule and aace_31r_compliance to run end-to-end from a plain clone. generate_xer_manifest additionally needs the internal audit-trail module, which is not bundled; see the note under the feature table.


License

MIT — see LICENSE.

You may use this parser in commercial forensic consulting, in academic research, in your own scheduling product, in court-filed expert reports. Just keep the copyright notice.


Contributing

See CONTRIBUTING.md. Bug reports and pull requests are welcome.


Companion repositories


Strategic note

Critical Path Partners is a forensic-scheduling consultancy. We open-source the foundational tooling because every academic, every solo forensic, every contractor's internal scheduler now has a reason to install CPP and a citation pathway. The math is a commodity; the workflow and discipline are not.

If you ship something built on this parser, we'd like to hear about it: criticalpathpartners.ca.

About

Critical Path Partners - canonical Primavera P6 XER parser and generator with MIP 3.4 half-step support

Topics

Resources

Contributing

Security policy

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages